Lake Shore Drive Drainage Improvements


 

City of St. Augustine Beach Public Notice

Lake Shore Drive Drainage Improvements

04/10/2026

This project has been completed.

SCOPE OF WORK

 

Deteriorating stormwater pipes on Lake Shore Drive between 16th and Willow Drive have caused both drainage and roadway problems for this area. Proposed maintenance improvements will include the replacement of approximately 300 linear feet of existing stormwater pipe, structures, and roadway, and curb and gutter.

 

CURRENT PROJECT PHASE: Complete

 

PROJECT FUNDING:

 

This is a City funded project.

 

SCHEDULE:

 

Tentative Dates, Weather Permitting

08/11: Construction Begins - Eastern Curb removal. COMPLETED 09/08 ✔️

08/18: Pipe Removal COMPLETED 09/30 ✔️

08/25: Pipe Placement COMPLETED 09/30 ✔️

09/15: New Curb Poured COMPLETED 10/06 ✔️ 

10/15: Additional Curb removed/replaced COMPLETED 10/22 ✔️

09/22: Paving COMPLETED 10/28 ✔️

09/29: Restoration COMPLETED 03/25 ✔️ 

10/06: Substantial Completion COMPLETED 01/07 ✔️ 

 

ADDITIONAL INFORMATION:

 

Contractor Information:

A.W.A. Contracting, Co., Inc.

100 Dragster Lane, St. Augustine, FL 32092

 

For additional project information, contact the City’s Engineering Department:

Jason D. Sparks, P.E.                                   Derek Sands

Engineering Director                                    Engineering Inspector

(904) 471-2122                                             (904) 808-5901

jsparks [at] cityofsab.org (jsparks[at]cityofsab[dot]org)                                dsands [at] cityofsab.org (dsands[at]cityofsab[dot]org)

 